City Awaits Home Ministry Reply Related to Flat Projects

Jakarta Provincial Government awaits reply from Home Ministry related with additional 90 days for five flats construction which are temporarily stopped.

The letter has been sent, but yet no reply

“The letter has been sent, but yet no reply. Now the contractors remain constructing the flat and will end the work in the end of this year,” said Acting Jakarta Governor, Sumarsono, Wednesday (12/14).

He explained the flat will be assessed by a team to asses working load. Jakarta Provincial Government will only pay the contractor based on the working load.

City Council Wants Postponed Projects to Be Audited

“If the project is not completed, we’ll pay them on based on the working load,” he added.

The remaining working will be continued next year without holding an auction.

“As the example, five percent of remaining work will be continued next year. It can be proposed in 2017 administration,” he closed.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye707 personBudhi Firmansyah Surapati
  2. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye666 personDessy Suciati
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye665 personDessy Suciati
  4. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye631 personNurito
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye629 personAldi Geri Lumban Tobing